Residential Building Permit in Bountiful, Utah
Required for new residential construction, additions, and structural alterations in Bountiful.
Verified 2026-06-27 · Source
When you need this permit
- Project valuation over $500
- New construction or structural modification
- Changes to electrical, plumbing, or mechanical systems
Required documents
- Req
Building Plans
Two sets of construction drawings to scale
- Req
Site Plan
Property survey showing setbacks and footprint
- Req
Energy Compliance
REScheck or equivalent energy calculation
- Req
Engineered Truss Plans
Sealed truss layouts for new construction
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Plan Review | 65% of building permit fee | — |
| Building Permit | Based on ICC valuation table | — |
| Utility Connection | Varies by connection type | — |
Review timeline
10–21 business days
Typical plan review in Bountiful
Inspection process
- 1
Foundation
Before concrete pour — forms, rebar, anchor bolts
- 2
Framing
After framing, sheathing, and roof — before insulation
- 3
Insulation
After insulation installed, before drywall
- 4
Final
All work complete, ready for occupancy
Tips
- Bountiful processes all permits through Cityinspect — submit your application online for fastest processing.
- Bountiful's office hours are Monday through Thursday only (4-day work week) — plan accordingly.
- Schedule inspections at least 24 hours in advance.
Frequently asked questions
- How much does a residential building permit cost in Bountiful?
- Bountiful uses the ICC building valuation table to calculate permit fees. Plan review is an additional 65% of the permit fee. Call (801) 298-6140 for a project-specific estimate.
- How long does permit review take in Bountiful?
- Residential plan review in Bountiful typically takes 10-21 business days. Submit through Cityinspect for the fastest processing.
Get the AI compliance checklist