Residential Building Permit in Orem, Utah

Required for new residential construction, additions, and structural alterations in Orem.

Verified 2026-06-27 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Plan Review65% of building permit fee
Building PermitBased on project valuation per ICC table
Utility ConnectionVaries by connection type

Review timeline

1021 business days

Typical plan review in Orem

Inspection process

  1. 1

    Foundation

    Before concrete pour — forms, rebar, anchor bolts

  2. 2

    Framing

    After framing, sheathing, and roof — before insulation

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete, ready for occupancy

Tips

Frequently asked questions

How do I apply for a residential building permit in Orem?
Orem requires all building permit applications to be submitted online through their Development Services portal. Paper submissions are not accepted. Contact (801) 229-7060 for assistance.
How long does permit review take in Orem?
Residential plan review typically takes 10-21 business days in Orem. Digital-only submission helps streamline the review process.